Council awards contract to design and oversee £5.7million Town Hall transformation

Westmorland and Furness Council has awarded a contract to design and oversee the proposed £5.74 million transformation of Penrith Town Hall into a Creative and Community Hub, although the future of the historic building still depends on a final decision by council leaders next year, just weeks before May's local elections.

The decision, signed off on 11 November, will see a specialist consultancy team appointed to develop the designs and oversee delivery of the proposed transformation of the Grade II listed building, which has stood empty since June 2024.

The contract covers the project from its initial design stages through to overseeing construction and completion, but the appointment does not mean the redevelopment itself has received final approval.

A total of 35 companies competed for the contract, with 34 submitting bids that met the council's requirements.

The council has set aside £450,000, excluding VAT, for the professional services contract, although the actual price agreed with the winning company has not been disclosed.

The identity of the successful bidder and the amount being paid have both been withheld by the council.

The contract is expected to begin on 14 December, or earlier if the necessary processes are completed, and will run for approximately 22 months.

The latest decision follows the council's Cabinet meeting in July, when councillors agreed to progress their preferred option for the Town Hall, known as Option 2C, to a Full Business Case.

That decision allowed work to continue on developing the proposed hub but stopped short of approving the redevelopment.

The council's plans would see the historic Town Hall transformed into a new centre for creative and community activities, bringing together cultural facilities, spaces for young people, improved access to some council services and a new home for Penrith Museum.

The project is being supported through funding secured from the Local Regeneration Fund and the Borderlands programme.

The £5.74 million estimated overall cost covers the proposed redevelopment of the building, rather than simply the design and consultancy work now being commissioned. The £450,000 professional services budget forms part of the wider project funding and should not be treated as an additional cost on top of the redevelopment estimate.

However, the £5.74 million remains an estimated project cost rather than a confirmed final price, with the detailed Full Business Case still to establish the financial position before Cabinet decides whether to proceed.

Despite the award of the latest contract, the future of the building remains undecided, with the Full Business Case still requiring Cabinet approval before the wider transformation can proceed.

The timing of that decision places the future of one of Penrith's most prominent public buildings in the run-up to the May 2027 local elections, when all seats on Westmorland and Furness Council will be contested.

The council had previously indicated that the Full Business Case would return to Cabinet in December 2026, but the final decision is now expected next year.

The latest contract award also highlights the financial commitment being made to progressing the proposals before a final decision on the redevelopment has been taken.

While the £450,000 professional services budget is part of the wider project funding, the actual contract value remains undisclosed, as does the detailed financial information contained in the council's confidential Outline Business Case.

The council has acknowledged that transforming the Grade II listed Town Hall presents particular challenges, with the historic nature of the building requiring specialist design work and listed building consent.

It has also warned that failing to proceed could result in further cost increases, put the funding already secured at risk and leave the building unoccupied.

Further consultation with residents and local organisations is expected as the detailed designs are developed.

The council says the proposed hub would support Penrith's cultural economy, create new opportunities for young people and provide improved community facilities in the town centre.

For now, the award of the contract moves the project another stage forward, but does not guarantee that the transformation will happen.

With an estimated £5.74 million redevelopment on the table, hundreds of thousands of pounds allocated to professional services and the final decision still to be made, the future of Penrith Town Hall remains in the hands of council leaders as next year's local elections approach.

Weather

7°C
Today, 2pm
Light Rain with -- mph Breeze from Direction not available
7°C
Thursday, 2pm
Sunny Intervals with -- mph Breeze from Direction not available
5°C
Friday, 2pm
Sunny with -- mph Breeze from Direction not available
advertisement-2.jpeg

National Headlines
National and International News Headlines...
Add Penrith.Town App. Press Then select "Add to Home Screen"